00000057-021 - Tidewater Midstream and Infrastructure Ltd.
Approved

Tidewater Midstream and Infrastructure Ltd. has requested an amendment to Ram River Sour Gas Plant approval under Environmental Protection and Enhancement Act to add a power generator and a compressor engine at the plant. Deadline for submitting a Statement of Concern is July 6, 2018 in the following location:

02-037-10W5M

 

00073203-008 - Williams Energy Canada ULC
Closed

Williams Energy Canada ULC has submitted a request to extend the expiry of the existing approval for their Fort McMurray Hydrocarbon Liquids Extraction Facility. The extension will allow the Alberta Energy Regulator time to review the renewal application that has been submitted in the following locations:

26-092-09W4M
12-092-10W4M

 

00387835-001 - Tidewater Midstream and Infrastructure Ltd.
Approved

Tidewater Midstream and Infrastructure Ltd. has submitted an application under Specified Enactments (Environmental Protection and Enhancement Act) for an approval to construct 25.15 km of 712 o.d. mm sweet natural gas pipeline called the Hythe Lateral Pipeline (west of Grande Prairie). The proposed pipeline right-of-way (ROW) will originate at a riser site at LSD 15 of Section 30 Township 71 Range 8 West of the 6th Meridian and will continue north to 2 separate riser sites located at LSD 6 of Section 19 Township 73 Range 8 West of the 6th Meridian and LSD 5 of Section 30 Township 73 Range 8 West of the 6th Meridian. The deadline for submitting a statement of concern is January 24, 2017 in the following locations:

30-071-08W6M
31-071-08W6M
06-072-08W6M
07-072-08W6M
17-072-08W6M
18-072-08W6M
20-072-08W6M
29-072-08W6M
30-072-08W6M
31-072-08W6M
06-073-08W6M
07-073-08W6M
18-073-08W6M
19-073-08W6M
30-073-08W6M
36-071-09W6M
01-072-09W6M

 

00017429-004 - Direct Energy Marketing Limited
Approved

An application has been submitted for a consent to transfer the existing Environmental Protection and Enhancement Act Code of Practice Registration for the Gilby Inlet Compressor Station from Direct Energy Marketing Limited to Canlin Energy Corporation. The deadline for submission of Statements of Concern is November 15, 2017 in the following location:

22-040-03W5M

 

00010801-013 - Gibson Energy ULC
Approved

Gibson Energy ULC has submitted an application under the Environmental Protection and Enhancement Act for an amendment of their existing approval of the Hardisty Terminal Bulk Petroleum Storage Facility. The amendment application is to obtain partial approval for the stripping and grading of the proposed development area to avoid impacts of winter construction and to obtain an approval for the construction of the six aboveground storage tanks. The deadline for submission of Statements of Concern is June 7, 2017 in the following locations:

08-042-08W4M
19-042-09W4M
20-042-09W4M
29-042-09W4M
30-042-09W4M

 

00381752-003 - Gibson Energy ULC
Approved

Amend a previously granted EPEA code of practice for Hydrostatic Testing in the following locations:

08-042-08W4M
19-042-09W4M
20-042-09W4M
29-042-09W4M
30-042-09W4M

 

00378455-003 - Keyera Energy Ltd.
Approved

Keyera Energy Ltd. has submitted an amendment application under the Environmental Protection and Enhancement Act for the Wapiti Sour Gas Plant to make some equipment changes at the Plant, which include the replacement of a 12,769 kW hot oil heater and the installation of two 220 kW salt bath heaters and a truck terminal incinerator. Deadline for submission of Statements of Concern is December 6, 2018 in the following location:

19-067-07W6M

 

00011066-036 - Prairie Mines & Royalty ULC
Approved

Joint notice with CCA application 1913374 and EPEA 036-11066 Prairie Mines & Royalty ULC has applied under sections 11 and 13 of the CCA to amend licence C90-2 and under sections 66 and 70 of EPEA to amend approval No. 00011066-02-09 for the Coal Valley mine. The amendments are to resume mining operations in pit 26 after 13 years of inactivity, modify the mine plan to expand pit 26 based on an updated resource model, align the mine’s existing water management plan with the modified mine plan, construct three dump sites, construct a new settling pond, and update the reclamation and closure plan. The mine is located about 100 kilometres south of Edson, in Township 47, Range 19, West of the 5th Meridian. The deadline for submitting a statement of concern is October 17, 2018 in the following locations:

01-046-19W5M
23-046-19W5M
26-046-19W5M
27-046-19W5M
28-046-19W5M
32-046-19W5M
33-046-19W5M
34-046-19W5M
35-046-19W5M
02-047-19W5M
03-047-19W5M
04-047-19W5M
05-047-19W5M
06-047-19W5M
07-047-19W5M
08-047-19W5M
09-047-19W5M
10-047-19W5M
15-047-19W5M
16-047-19W5M
17-047-19W5M
18-047-19W5M
19-047-19W5M
20-047-19W5M
30-047-19W5M
31-047-19W5M
33-046-20W5M
02-047-20W5M
03-047-20W5M
04-047-20W5M
09-047-20W5M
10-047-20W5M
11-047-20W5M
16-047-20W5M
17-047-20W5M
19-047-20W5M
20-047-20W5M
24-047-20W5M
26-047-20W5M
27-047-20W5M
28-047-20W5M
29-047-20W5M
30-047-20W5M
35-047-20W5M
07-048-20W5M
08-048-20W5M
18-048-20W5M
24-047-21W5M
25-047-21W5M
26-047-21W5M
34-047-21W5M
35-047-21W5M
36-047-21W5M
03-048-21W5M
04-048-21W5M
08-048-21W5M
09-048-21W5M
13-048-21W5M
17-048-21W5M
18-048-21W5M
19-048-21W5M
23-048-21W5M
24-048-21W5M
26-048-21W5M
27-048-21W5M
28-048-21W5M
30-048-21W5M
32-048-21W5M
33-048-21W5M
34-048-21W5M
04-049-21W5M
05-049-21W5M
06-049-21W5M
07-049-21W5M
13-048-22W5M
24-048-22W5M
25-048-22W5M
26-048-22W5M
27-048-22W5M
31-048-22W5M
32-048-22W5M
33-048-22W5M
34-048-22W5M
35-048-22W5M
36-048-22W5M
01-049-22W5M
02-049-22W5M
03-049-22W5M
04-049-22W5M
05-049-22W5M
06-049-22W5M
07-049-22W5M
11-049-22W5M
12-049-22W5M
13-049-22W5M
14-049-22W5M
01-049-23W5M
02-049-23W5M
03-049-23W5M
09-049-23W5M
10-049-23W5M
11-049-23W5M
12-049-23W5M
15-049-23W5M
16-049-23W5M
17-049-23W5M

 

00151469-010 - Fort Hills Energy Corporation
Approved

Suncor has applied on behalf of Fort Hills Energy Corporation under sections 10 and 13 of OSCA to amend OSCA Approval No. 9241E, under sections 66 and 70 of EPEA to amend EPEA Approval No. 151469-01-00 and under section 42, subsection 1b(i) of the WA to amend WA Approval No. 151636-01-00. These amendments have been requested in order to modify the mine plan to optimize the pit configuration and sequencing, align the mine plan with the tailings management plan, improve saline basal water management, incorporate the amended project area into each approval, and update the reclamation and closure plan. The Fort Hills mine is located about 80 km north of Fort McMurray and about 25 km north of Fort McKay within Townships 96, 97, and 98; Ranges 9, 10, and 11; West of the 4th Meridian, within the Regional Municipality of Wood Buffalo in the following locations:

19-096-09W4M
29-096-09W4M
32-096-09W4M
05-097-09W4M
06-097-09W4M
07-097-09W4M
08-097-09W4M
16-097-09W4M
17-097-09W4M
18-097-09W4M
19-097-09W4M
20-097-09W4M
21-097-09W4M
28-097-09W4M
29-097-09W4M
30-097-09W4M
31-097-09W4M
32-097-09W4M
33-097-09W4M
04-098-09W4M
05-098-09W4M
06-098-09W4M
07-098-09W4M
08-098-09W4M
09-098-09W4M
15-098-09W4M
16-098-09W4M
17-098-09W4M
18-098-09W4M
19-098-09W4M
20-098-09W4M
29-098-09W4M
30-098-09W4M
31-098-09W4M
32-098-09W4M
05-099-09W4M
06-099-09W4M
31-094-10W4M
05-095-10W4M
08-095-10W4M
17-095-10W4M
18-095-10W4M
19-095-10W4M
30-095-10W4M
05-096-10W4M
06-096-10W4M
07-096-10W4M
08-096-10W4M
14-096-10W4M
15-096-10W4M
16-096-10W4M
17-096-10W4M
18-096-10W4M
19-096-10W4M
20-096-10W4M
21-096-10W4M
23-096-10W4M
24-096-10W4M
26-096-10W4M
27-096-10W4M
28-096-10W4M
29-096-10W4M
30-096-10W4M
31-096-10W4M
32-096-10W4M
33-096-10W4M
34-096-10W4M
35-096-10W4M
01-097-10W4M
02-097-10W4M
03-097-10W4M
04-097-10W4M
05-097-10W4M
06-097-10W4M
07-097-10W4M
08-097-10W4M
09-097-10W4M
10-097-10W4M
11-097-10W4M
12-097-10W4M
13-097-10W4M
14-097-10W4M
15-097-10W4M
16-097-10W4M
17-097-10W4M
18-097-10W4M
19-097-10W4M
20-097-10W4M
21-097-10W4M
22-097-10W4M
23-097-10W4M
24-097-10W4M
25-097-10W4M
26-097-10W4M
27-097-10W4M
28-097-10W4M
29-097-10W4M
30-097-10W4M
32-097-10W4M
33-097-10W4M
34-097-10W4M
35-097-10W4M
36-097-10W4M
01-098-10W4M
02-098-10W4M
03-098-10W4M
04-098-10W4M
05-098-10W4M
09-098-10W4M
10-098-10W4M
11-098-10W4M
12-098-10W4M
13-098-10W4M
14-098-10W4M
15-098-10W4M
22-098-10W4M
23-098-10W4M
24-098-10W4M
25-098-10W4M
26-098-10W4M
27-098-10W4M
35-098-10W4M
36-098-10W4M
01-099-10W4M
25-095-11W4M
36-095-11W4M
01-096-11W4M
11-096-11W4M
12-096-11W4M
13-096-11W4M
14-096-11W4M
23-096-11W4M
24-096-11W4M
25-096-11W4M
26-096-11W4M
36-096-11W4M
01-097-11W4M
12-097-11W4M
13-097-11W4M

 

00246293-005 - Enercapita Energy Ltd.
Approved

Enercapita Energy Ltd. has submitted an application under the Environmental Protection and Enhancement Act for a renewal of their existing approval of the Boundary Lake 10-19 Sour Gas Plant. The deadline for submission of Statements of Concern is February 6, 2019 in the following location: