00351750-001 - Harvest Operations Corp.
Approved

Construction and operation of 6MW thermal electric power plant which would provide power to the Bilbo Sweet Gas Processing Plant in the following locations:

23-065-07W6M
24-065-07W6M
25-065-07W6M
26-065-07W6M

 

00205203-006 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has applied for an amendment of their EPEA Approval for the Bilbo Sour Gas Plant. The amendment is to request a second extension to the expiry of their existing approval. Deadline for submission of Statements of Concern is March 27, 2015 in the following location:

28-064-06W6M

 

00016921-009 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has applied for an amendment of their EPEA approval for the Provost Sour Gas Plant. The amendment is to request an extension to the expiry date of their existing approval in the following location:

15-040-08W4M

 

00205203-005 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has applied for a renewal of their existing EPEA approval. The renewal is for decommissioning and reclamation of Bilbo Sour Gas Plant. Deadline for submitting Statements Of concern is May 24, 2015 in the following location:

28-064-06W6M

 

00016921-008 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has submitted an application under the Enviromental Protection and Enhancement Act for a renewal of an existing approval for the Provost Sour Gas Plant. The plant was constructed to conserve and process 49.6 103m3/day of raw sour solution gas from oil batteries in the area. The sour gas plant is currently shut in and there are no plans to activate the gas plant. The solution gas is currently being compressed and piped to the Husky Thompson Lake Battery. All the equipment associated with the gas plant remains on site, but has not been blinded off to date. The deadline for submitting a statement of concern is January 19, 2015 in the following location:

15-040-08W4M

 

00000198-008 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has submitted an application under the Environmental Protection and Enhancement Act to transfer the ownership of the Badger Sour Gas Plant located in LSD 13 of Section 19 Township 16 Range 17 West of the 4th Meridian (approximately 21 km east of Lomond) from Harvest Operations Corp. to Little Rock Resources Ltd in the following location:

19-016-17W4M

 

00001426-003 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has submitted an application under Specified Enactments (Environmental Protection and Enhancement Act) to transfer the ownership of the Bolloque Compressor Station located in LSD 16 of Section 23 Township 64 Range 26 West of the 4th Meridian (in the Westlock Area) from Harvest Operations Corp. to Canadian Natural Resources Limited in the following location:

23-064-26W4M

 

00001414-006 - Harvest Operations Corp.
Approved

An application has been submitted for a consent to transfer the existing Environmental Protection and Enhancement Act Code of Practice Registration for the Shiningbank Sweet Gas Plant from Harvest Operations Corp. to ISH Energy Ltd. The deadline for submission of Statements of Concern is March 1, 2018 in the following location:

12-056-17W5M

 

00176900-002 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has submitted an application under the Environmental Protection and Enhancement Act to update the registration for the Alexis Oil Battery and Solution Gas facility located in LSD 6 of Section 36 Township 55 Range 5 West of the 5th Meridian (southeast of Cherhill). The updated registration indicates the eqipment that is currently on site in the following location:

36-055-05W5M

 

00246984-004 - Harvest Operations Corp.
Approved

Harvest Operations Corp. has submitted an application under the Environmental Protection and Enhancement Act for an extension to an existing approval for the BlackGold SAGD Project. The facility commenced start-up in 2018 and do not have a full year of operational data in order to complete a renewal application. The extension will allow operational data to be collected in the following locations:

01-076-07W4M
03-076-07W4M
10-076-07W4M
11-076-07W4M
12-076-07W4M
13-076-07W4M
14-076-07W4M
15-076-07W4M
22-076-07W4M